NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: September 29th – October 3rd, 2025
Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.
Key Phases & Timeline
Monday, September 29th to Friday, October 3rd, 2025
Construction Activities:
Pipeline Crew #1:
Grand Street between 13th Street and 14th Street
Installation of water main valve
14th Street between Grand Street and Clinton Street (including intersections)
Installation of piles, pile caps, and pipe cradles
Installation of storm sewer pipe, manholes, and inlets
Pipeline Crew #2:
14th Street between Grand Street and Clinton Street (including intersections)
Relocation of 8" water main and other utilities
Installation of piles, pile caps, and pipe cradles
Installation of storm sewer pipe, manholes, and inlets
15th Street and Clinton Street intersection
Relocation of combined sewer
Relocation of PSE&G gas
Restoration Crew:
13th Street and Adams Street (northeast corner – 13th St remains open)
Sidewalk and Curb restoration
Traffic Management:
Grand Street between 13th and 14th Street
Road to be closed during working hours (8 am - 6 pm)
Roadway changed to 2-Way traffic (north and south) to allow access to resident garages.
14th Street between Grand Street and Clinton Street (including intersections)
Road to be closed 24 hours, 7 days/week
15th Street and Clinton Street intersection
15th Street will be open and allow alternating traffic assisted by Hoboken Officers
Temporary Parking Impacts:
Grand Street between 13th and 15th Street
No parking east of the street (24/7)
Clinton Street between 14th Street and 15th Street
Temporary no parking east side of the street, south half, from14th St to 15th St (6am - 6 pm)
15th Street and Clinton Street intersection
Temporary no parking both sides of the both streets – 70’ in all directions (6am - 6 pm)
We appreciate your patience and cooperation as we work to improve our infrastructure.