NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: September 8th – September 12th, 2025

Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.

Key Phases & Timeline

  • Monday, September 8 to Friday, September 12, 2025

Construction Activities:

Pipeline Crew #1:

  • Grand Street between 13th Street and 14th Street (Monday, September 8 to Friday, September 12, 2025)

    • Installation of piles, pile caps, and pipe cradles

    • Installation of 36" Storm pipe

    • Installation of manholes

Pipeline Crew #2:

  • Clinton Street between 13th Street and 14th Street  (Monday, September 8, 2025 to Wednesday, September 10, 2025)

    • Cobblestone roadway restoration

    • Roadway temporary paving

Pipeline Crew #3:

  • 15th Street and Clinton Street (1 day - TBD by PSE&G Schedule)

    • Excavation for PSE&G gas relocation.  Currently scheduling with PSE&G

Traffic Management:

  • Grand Street between 13th and 14th Street

    • Road to be closed during working hours (8 am to 6 pm)

    • Roadway changed to 2-Way traffic (north and south) to allow access to resident garages.

  • Clinton Street between 13th Street and 14th Street

    • Road to be closed during working hours (8 am to 6 pm)

  • 14th Street between Grand Street and Clinton Street

    • Road to be closed during working hours (8 am to 6 pm) 

Temporary Parking Impacts:

  • Grand Street between 13th and 14th Street

    • Temporary no parking both sides of the street (24 hours, 7 days/week)

    • Access to resident garages will be available during working hours and non-working hours.

  • 13th Street between Adams Street and Clinton Street

    • Temporary no parking both sides of the street (Monday - Friday, 6 am to 6 pm)

  • Clinton Street between 13th Street and 14th Street

    • Temporary no parking both sides of the street (24 hours, Monday to Wednesday)

    • Access to resident garages/driveways will be available during working hours and non-working hours.

  • Clinton Street between 14th Street and 15th Street

    • Temporary no parking East side of Clinton Street only (Thursday and Friday, 6 am to 6 pm)

  • 15th Street and Clinton Street Intersection

    • Temporary no parking; 50 feet in all directions from centerline of intersection

We appreciate your patience and cooperation as we work to improve our infrastructure.

Previous
Previous

Madison Street Infrastructure Improvements: Construction and Traffic Management Activities Week of September 8, 2025

Next
Next

NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: September 1st – September 5th, 2025